Product management for engineers · Chapter 4 of 10 · Product · new chapter every Wednesday morning
By the end of this chapter: Use a scoring method honestly, including its limits.
The problem
You are the lead engineer for a core services team. It is Tuesday afternoon, and you are staring at a Jira backlog containing 412 issues. Of those, 85 are marked "High Priority," and 12 are "Critical." Your team of five can realistically complete four to six substantial tasks per sprint.
Last month, the priority was "Project Alpha" because the CTO promised it to the board. This morning, the Product Manager (PM) moved three new tickets to the top of the sprint because a Tier-1 customer threatened to churn if they didn't get a specific API extension. Meanwhile, your lead frontend dev is warning that the build pipeline is so brittle that it fails 40% of the time, costing the team roughly six hours of productivity per week.
The PM asks you to "just fit the API extension in." You know that doing so means Project Alpha will slip, the build pipeline will remain broken, and the team will likely work through the weekend to meet the original deadline. The cost isn't just a missed date; it is the erosion of trust. When everything is a priority, nothing is a priority, and the backlog becomes a graveyard of half-finished ideas and broken promises.
You need a way to move the conversation from "Can we do this?" to "Is this more valuable than what we are currently doing?" You need a scoring mechanism that survives a meeting with a frustrated stakeholder.
Before you start
To follow this chapter, you need a list of at least five competing tasks or features. For this exercise, we will use a spreadsheet (Google Sheets or Excel) to calculate scores.
- Create a spreadsheet with the following columns: Feature Name, Reach, Impact, Confidence, Effort, and RICE Score.
- Ensure you have the "Problem Statements" developed in Chapter 3 for at least two of these items.
To verify your setup, enter a dummy row. If you set the formula for RICE Score to (Reach * Impact * Confidence) / Effort, and enter Reach=1000, Impact=2, Confidence=0.8, and Effort=2, your RICE Score should be 800.
Why your backlog is a lie
The primary reason backlogs fail is that they are treated as a "to-do list" rather than a "selection pool". A to-do list implies an obligation to finish everything. A selection pool acknowledges that you will likely delete 80% of what is inside it.
In my experience, a backlog larger than two months of work is a liability. It creates a "shadow work" effect where engineers spend time grooming, discussing, and thinking about tickets that will never be built. This is the "Backlog Lie": the belief that by writing a ticket down, you have captured value. In reality, you have only captured a distraction.
Prioritisation is not about finding the "best" thing to do; it is about creating a defensible reason to say "no" to things that are merely "good." To do this, you must move away from subjective labels like "High/Medium/Low" and toward a model that forces stakeholders to quantify their assumptions.
The mechanics of RICE
We use the RICE framework (developed by Intercom) because it specifically penalises "gut feelings" through the Confidence score.
- Reach: How many people will this affect in a given timeframe (e.g., per quarter)?
- The number: Use real data. "All 5,000 active users" or "The 50 users who use the admin panel daily."
- Impact: How much will this contribute to the goal?
- The scale: 3 for "massive impact," 2 for "high," 1 for "medium," 0.5 for "low," and 0.25 for "minimal."
- The trade-off: If you claim a 3, you must be able to explain how it moves a top-level metric (e.g., conversion or retention).
- Confidence: How sure are you about your estimates?
- The scale: 100% is "high confidence" (we have user data and a technical POC). 80% is "medium." 50% is "low" (it’s a guess).
- The reality: Anything below 50% is a "moonshot" and should be treated as a research spike, not a feature.
- Effort: How much time will this take from the whole team (Product, Design, Engineering)?
- The unit: Person-months. A task that takes one engineer two months is 2.0. A task that takes two engineers one week each is 0.5.
The formula (R * I * C) / E gives you a score representing "Value per unit of time."
Build it: The Honest Prioritisation Matrix
You will now build a scoring matrix for your current workload. This process forces the PM and the Lead Engineer to align on the why before the how.
Step 1: Quantify Reach
For each item in your list, assign a Reach number based on the last 30 days of user data.
- Action: Look at your analytics tool (e.g., PostHog, Mixpanel, or SQL logs).
- Why: To stop "loudest user" bias. A bug affecting 5 users is different from a bug affecting 5,000.
- Confirm: You have a number in the Reach column that is not a round "guess" like 1,000.
Step 2: Assign Impact with a "Why"
Assign an Impact score (0.25 to 3).
- Action: For every score above 1, write one sentence explaining the metric it moves.
- Example: "Impact 3: This reduces onboarding drop-off by automating the SSH key upload, which currently accounts for 40% of support tickets."
- Confirm: Every item has a score and a justification.
Step 3: The Confidence Audit
This is where the lead engineer exerts the most influence.
- Action: Review the PM’s Confidence score. If there is no technical design or user research, set it to 50%.
- Why: This is the "honesty filter." It heavily penalises features that are poorly defined.
- Confirm: If you have never built a similar integration before, your Confidence score cannot be 100%.
Step 4: Estimate Effort in Person-Months
- Action: Provide a rough engineering estimate. Do not use story points; use time.
- Why: Stakeholders do not understand points. They understand that a 4.0 effort means the team is busy for a month.
- Confirm: The Effort column is populated.
Step 5: Calculate and Sort
- Action: Apply the formula
(R * I * C) / E. Sort the table by the RICE Score (Descending). - The Result: You now have a list where the top items provide the most "bang for buck."
Feature,Reach,Impact,Confidence,Effort,RICE Score API Extension,50,3,0.8,0.5,240 Build Pipeline Fix,500,2,1.0,0.25,4000 Project Alpha,5000,2,0.5,4.0,1250 CSV Export,200,1,1.0,0.5,400 In this scenario, the Build Pipeline Fix (4000) is the clear winner, despite the PM wanting the API Extension (240). The data shows the pipeline fix helps more people, more reliably, for less effort.
When this breaks
The "Impact Inflation"
Symptom: Every feature is marked as "Impact: 3 (Massive)."
Cause: Stakeholders are gaming the system to get their pet project to the top.
Fix: Implement a "Points Budget." In a list of 10 items, only 2 can be an Impact 3. This forces a forced ranking. If everything is a 3, nothing is a 3.
The "Effort Underestimation"
Symptom: Engineering consistently says things will take "one week" (0.25), but they take three.
Cause: Ignoring the "Definition of Done" (testing, docs, deployment).
Fix: Multiply all initial engineering estimates by 1.5 or 2.0 before putting them in the spreadsheet. In my experience, this "reality factor" produces a RICE score that actually reflects delivery.
The "CEO Override"
Symptom: A project has a RICE score of 10, but the CEO says it must be done by Friday.
Cause: High-level strategic shifts or "Founder Intuition."
Fix: Do not try to fight this with the spreadsheet. Instead, use the spreadsheet to show what is being dropped. "We can do the CEO project, but it means the Build Pipeline Fix (Score: 4000) and Project Alpha (Score: 1250) are now off the table for this quarter. Are we okay with that?"
What it costs
Using a scoring model is not free. It introduces friction.
- Analysis Paralysis: You can spend more time arguing over whether Reach is 400 or 500 than it would take to build the feature. Set a time limit (e.g., 30 minutes) for scoring sessions.
- Bias Against Big Bets: RICE naturally favours small, high-certainty wins (low Effort, high Confidence). This can lead to a "local maximum" where you never build the difficult, transformative features (High Effort, Low initial Confidence) that actually grow a business.
- The "Maintenance" Tax: Technical debt rarely has a high "Reach" in terms of end-users, so it often scores poorly. You must carve out a fixed percentage of capacity (e.g., 20%) for engineering-led tasks that bypass the RICE process entirely.
In the interview
In an interview for a Senior or Staff role, the question "How do you prioritise work?" is a trap designed to see if you understand business constraints.
Weak Answer: "I look at the Jira tickets and pick the ones with the highest priority label, or I ask the PM what they want."
Why it's weak: It shows a lack of agency. You are a passenger, not a partner. It assumes the labels are correct.
Strong Answer: "I use a weighted scoring model like RICE to facilitate a trade-off conversation. I focus on the 'Confidence' and 'Effort' metrics because those are where engineering has the most signal. I look for the 'Value per unit of Effort' rather than just 'Value.' I also ensure we reserve capacity for non-functional requirements that scoring models typically undervalue."
The Senior/Staff distinction: A senior engineer explains how they score a feature. A Staff engineer or EM explains how they handle the politics of the score—how they use the data to negotiate with a VP of Sales who wants to jump the queue, and how they protect the team from "priority churn."
The Follow-up: "What do you do when the data says one thing, but your intuition says another?"
The answer: You use a "Research Spike." If your intuition says a low-scoring item is important, your Confidence score is likely the problem. You spend two days gathering data or building a prototype to move that Confidence from 50% to 80%. If the score doesn't move up, your intuition was wrong.
Your tasks
- Score your current sprint: Take your current active tasks and put them into the RICE matrix. Does the order match your current "Priority" labels?
- The Sensitivity Test: Take your highest-scoring item. Double the Effort estimate. Does it still stay at the top? If not, your plan is "brittle" and relies on perfect execution.
- The "Kill" List: Find the bottom 20% of your backlog by RICE score. Write a one-paragraph justification for deleting them entirely. Present this to your PM.
- The Confidence Gap: Identify one task where the PM has "High Confidence" but you have "Low Confidence" in the technical implementation. List three specific questions that, if answered, would move your confidence to 90%.
Your tasks this week
Do the exercises above before the next chapter. Reading a tutorial and doing
one are different activities and only one of them changes what you can build.
Stuck on any of them? Say so — describe what you tried and what happened:
tell me where you got stuck. I read every one, and the questions
that come back more than twice get answered in the next chapter.
Product management for engineers
Chapter 4 of 10. New chapter every Wednesday morning.
Next: Roadmaps that survive contact with reality.
· The full syllabus and every chapter so far
· Subscribers also get the condensed notes for this chapter, the running
recap of everything the series has covered, and the extended guidance:
subscribe
Written by Amit Chakraborty — founding engineer and senior architect: React Native, AI and RAG systems, production architecture. Portfolio · LinkedIn · GitHub.